Resource Tracking

Resource Tracking

The resource scheduling as per 6.1.8.3 is required to be tracked to monitor actual deployment and deviations, if any with respect to baseline plan of the project. The impact of deviation may be correlated to deviation in rate of performance of activity. The resources to be tracked include the following three components are:

a) Manpower, with breakup of skill and trade;

b) Material, that are required for the project including the enabling works material; and

c) Plant and Equipment, that are to be deployed as per the baseline plan. The resource tracking process shall determine,

a) the status of deployment of all resources planned versus the actual.

b) the variation in resource productivity considered during planning stage and actual achieved.

c) impact of variation in resource productivity and revised requirement of the resources for on-going and future activities.